Work trip at the Plishner antenna site, Saturday November 16, 2019

Text and photos by Gary Agranat.

As we do each third weekend of the month, we had a scheduled work day at our DSES Plishner radio astronomy antenna site in Haswell, Colorado. Our members who participated on this weekend were Steve Plock, Ed Corn, Ray Uberecken, and Gary Agranat. Work objectives were:

  • Completion of installing the antennas and cables on the new 50 foot ham radio antenna tower.
  • Servicing the 60-foot dish antenna feed.
We typically meet first at the Ellicott firehouse for carpooling, before heading to the Plishner site.

I will save discussion of the 60-foot antenna feed for the Engineering Meeting minutes. That work was done by Steve Plock and Ray Uberecken. In this post I will describe the work we completed for the 50 foot tower.

The 60-foot dish antenna was rotated to the service tower, to enable Steve to work at the feed point.

For our 50-foot tower work, we installed a second vertical antenna for normal contacts on the 2-meter VHF band. This gives us a second 2-meter band capability, independent of our already existing 2-meter band talk-in radio. We then installed coax cables for both of the 2 meter band antennas on the tower.

We also serviced the 80 and 160 meter band dipole antennas that the tower supports: 1) We replaced some of the nylon rope that lifts the dipole antennas to their deployed positions. Previously we had connected shorter pieces of rope and knotted those together. But the knots stuck in the pulleys, and we therefore replaced those with longer sections of rope without knots. 2) We neatened the arrangement of the wire antennas supported by the tower.

Captions to the photos provide more detials of the work.

Ed and Gary lowered the 50-foot ham radio tower. A second VHF 2-meter band vertical antenna was added to the side of the tower, in addition to the VHF talk-in radio antenna placed last month at the top of the tower. And coax cables were added that feed both VHF antennas.
The second VHF 2-meter band antenna was added here, at this upper location along the side of the tower. Two stand-off support arms were bolted to the tower. Then the antenna was connected to its mast, which fits from below as a sleeve fitting. And the mast was connected to the supports. The mast serves both for structural support and as a counterpoise.
The tower raised up again.
The tower supports these ham radio antennas.
The tower supports the 160 meter band and 80 meter band dipole antennas by rope and pulley systems. The 160 meter antenna is oriented east-west, and the 80 meter antenna is oriented perpendicularly north-south.
Ed’s work truck on site.

After we serviced the ham and radio astronomy antennas, Steve made us lunch by smoking beef sausage in the grill. That was served with coleslaw and potato salad. Gary also brewed coffee.

After the tower was raise back up, Gary operated on phone and FT8, using the tri-band Yagi on 15 and 20 meters, and using the 80 and 160 meter dipoles. (10 meters was tried also but with no results, likely due to the poor propagation conditions.) The operating was in part for fun, and in part to verify that the antennas we put back up functioned properly. They all functioned well.

After lunch I did some ham radio operating using the tri-band Yagi, and also the using the 80 and 160 meter dipoles.  With the tri-bander, I first made a phone contact to Hawaii on 15 meters, before the bands got busy with the ARRL sweepstakes.  Then I operated FT8: on 15 meters I mostly contacted South American stations (lots of Brazil), plus some US stations when they were there (including North Carolina and Montana).  On 20 meters the band opened across the Pacific.  We had many calls to us from Japan. Perhaps they saw our profile on QRZ, or perhaps they noticed our rare grid square.  Also across the Pacific, we made two contacts with South Korea, one with mainland China, one with Indonesia, and one with Australia.  The band became weaker for US and Canadian contacts, but we did have some of those too.  I alternated going to 80 meters, and had a few more domestic contacts there. These were with our K0PRT station callsign. Later I also used my callsign, on 20, 80, and 160 meters. 160 meters had noise at the FT8 frequencies. But I went to the upper portion of that section of the band, which was just slightly better. I managed 4 contacts on 160 meters, to as far away as Kentucky. I would say our antennas were working well.

Within a few days we received a number of e QSL confirmation cards.

The site at the end of the day.

Ray left after lunch. Ed and Steve left before sunset. Steve tested the range of the new talk in radio antenna on the tower as he and Ed drove home away from the site. We had good contact to as far away as Sugar City. At JRs in Ordway, we could hear each other, but Steve needed to turn off his squelch. And at that point there were some slight dropouts. But we could still communicate. That is a great improvement for our talk-in system. Gary stayed and operated the ham station until a little after dark, and then closed up and departed too.

Antenna Raising

Plishner Antenna Site Work Trip Report. By Gary Agranat. Photos by Steve Plock.

Ed Corn, Steve Plock, and Gary Agranat traveled to the Plishner antenna site in Haswell this past Saturday, October 19, 2019. The team completed erecting the 50-foot ham radio tower.

Completing the tower erection involved several tasks:

  • Installing the 3-band/3-element Yagi HF ham antenna,
  • Installing the 2-meter band vertical antenna on top of that mast. This will be our new antenna for our VHF talk-in radio system.
  • Installing two stand-off bracketed supports near the top of the tower on the sides, to raise and hold the 80 meter band and 160 meter band dipole wire antennas. This arrangement replaces the long pole that previously centrally supported those wire antennas. These bracket supports each have a pulley and rope, to raise and lower the wire antennas. The tower also supports a 6-meter band delta-loop antenna, which is simply tied from height.
  • Securing the coax cables for the Yagi and vertical antennas along the side of the tower.
  • Properly arranging the system of wires, coaxes, and support cables.
  • Raising the 50-foot tower, which involves turning the winch system that rotates the tower up from its pivot plate at its base. The 50-foot tower is raised from a pulley system on a second smaller adjacent tower.
  • Once the 50-foot tower is raised, securing 3 guy cables.
Steve took this photo of Ed and Gary at the completion of the tower raising.

Steve tested the SWR of the 3-band Yagi antenna with an analyzer. The antenna elements had been measured and assembled on a previous trip, to be optimized for the middle of each of the operating bands, of the 10, 15 and 20 meter bands. Steve measured an SWR ratio of 1:1 (perfect) at 28.51 MHz for the 10 meter band, and 1:1 at 21.19 MHz for the 15 meter band. The 20 meter band resonated with an SWR of 1:1.35 at 14.16 MHz. This is excellent, and as expected.

For lunch, Steve treated us with smoked ribs from Broken Bones BBQ in Monument, with sauces, potato salad, and coleslaw. Gary brewed coffee. Also, the team met first at the firehouse in Ellicott. Gary baked orange-cranberry muffins. We ate our muffins at the firehouse, and shared the rest with the fire department crews there.

The team left the Plishner site by 4:30 pm.

The tower work began about a year ago. The work involved support and efforts by a number of team members. See our past posts from October 19-21, 2018 http://dses.science/plishner-site-report-for-the-weekend-of-october-19-21-2018, August 24, 2019 http://dses.science/plishner-work-trip-report-august-24-2019, and September 28, 2019 http://dses.science/work-site-trip-report-at-the-haswell-plishner-radio-telescope-site-september-28-2019.

The tower should significantly improve our capability to communicate long distances on the 10, 15, and 20 meter bands with the Yagi. The 2 meter band vertical should enable us to communicate on our talk-in VHF radio system to much further out.

Work Site Trip Report, at the Haswell Plishner Radio Telescope Site, September 28, 2019

by Gary Agranat

DSES Participants: Gary Agranat, Ed Corn, Bob Haggard, Bill Miller, Steve Plock.

Ed, Gary, and Bill met first at the Ellicott Fire Department, while Steve and Bob each traveled ahead solo. Ed encountered a problem with his truck and had to return home, but he passed the tower antenna mast and connector supplies to Bill. Steve and Bob arrived at the site by 9 AM, and Bill and Gary arrived by 10 AM.

We encountered light drizzling rain and low clouds on the route to the site, but the rain let up once we were on Highway 96 past Ordway. Steve called Ed to let us know the weather was good at the site. The weather completely cleared later, while the temperature remained comfortable.

Steve coordinated by phone with Skip Crilly and commenced a 48-hour long SETI drift scan at -7.5 degrees declination, run simultaneously with Skip’s antenna in New Hampshire. The 48 hour run will scan the -7.5 degree declination band twice, and therefore acquire a repeat set of data that can be compared with the first set.

Bob worked at the Communications Trailer, doing carpentry and painting work. He built a wood frame seal around one of the air conditioners, fabricated and painted a seal for the solar-powered fan, and painted the third work table he had added previously. Bob told me the trailer back door hadn’t been sealing — until recently — because it actually had not been closed properly. He closed the door properly and it is now sealed, without requiring further work.

Bob at work.

Bill, Steve, and Gary worked on preparing the 50-foot ham radio antenna tower.

Bill spliced the controller feed cable and wires for the antenna rotator, and verified proper operation, with some assistance from Gary. Bill used Steve’s crimping tools. The three of us then fed the controller cable through the dog house to the tower.

Bill first checked online for the correct color code standards for the control cable wiring. Then he matched the correct colored wires from the cable to the wires on the rotator. After the wiring was completed, the rotator and controller were tested for correct operation and correct meter calibration.

At the tower outside, the rotator was attached to its base plate, and that assembly was then attached to the tower.

When we tried to fit the mast in the holding tube at the top of the tower, we found that top opening was slightly damaged, and the mast wouldn’t fit in. We then took turns filing and grinding out the hole until the mast did fit properly. Steve applied a lubricating grease, to mitigate against the mast binding stuck when rotating. Eventually we successfully installed the mast to the rotator itself. We also retrieved a guy wire cable left at the communications trailer and attached it as the third guy wire connection for the top of the tower.

Bill with Steve, filing out the top opening for the mast. You can see two of the three guy cables already attached to the top of the tower.
Steve
Gary
Bill and Steve fitting the mast at the tower top. The mast was then securely fastened to the rotator.
The 60 foot antenna positions at 39.5 degrees elevation for the 48-hour SETI run, in progress.

Before we left for the day, we had two visitors from Eads come to look at the site. We all spent a little while talking about the site and the work.

Addendum

By Gary Agranat

Bob was the first to leave, then Steve. Steve said he would check on Ed on the way home. Bill and I (Gary) convoyed out last.

While Bill and I were driving back to Colorado Springs, about an hour and a half into the trip back, an auto accident happened right in front of us, with a vehicle overturning.

The accident happened while we were driving westbound on Colorado Highway 94. It was early evening by then, about 5:30 pm, and the sun appeared above in the western sky. Bill and I had been talking on the VHF ham radio during our 2 1/2 hour drive back from the site. Bill was driving ahead of me.

A couple of miles before Rush, I saw three vehicles approaching from a long distance behind, moving faster than Bill and me, while we were going at about the speed limit. I mentioned the vehicles to Bill, and we stopped talking, anticipating they would choose to pass us soon. They did soon pass us, all three staying close to each other. We could see they were some sort of laborers, with equipment filling their vehicles and with ladders on top. The third vehicle passed us as we were going up a hill, with the solid yellow line on our side. Bill commented that car was taking risks, although they all were driving in a risky manner. There was no visibility over that hill. And furthermore we were driving into the sun. A couple of miles later we reached the town of Rush, where the speed limit lowers from 65 to 50 mph. As those three vehicles ahead approached the town, I suddenly saw the last one veer to the left side of the road, and then roll over, with its front turned facing the opposite direction. Bill and I both stopped, as did a driver heading in the oncoming direction who almost got hit. And several more cars stopped briefly. We saw one occupant lie in the grass, but he eventually got up.

Bill had a better view of the accident ahead of me. It looked to him like one of the three vehicles ahead suddenly slowed as he reached the town with the lower speed limit. The sun was right above and ahead of us, which created a greater visibility challenge. The sudden slowing apparently caught the last driver off guard, as he swerved to the right to avoid the vehicle ahead of him. But that put his right side of his car in the grass there, which caused a tire blowout and a swerve then to the left. And he overturned.

The volunteer fire department nearby responded relatively quickly. But we waited about 2 hours for a sheriff’s deputy to arrive, and then another hour for a State Patrol officer to arrive. The State Patrol was who we had to give our witness statements to. We didn’t finish with that until 8:30 pm, and I didn’t get home until 9:30.

The driver of the overturned vehicle eventually got up, but he refused medical help, although we wondered if he nonetheless might have been hurt.

Meanwhile the communities there are small, and everyone there knows everyone else. The other driver who stayed was a local woman school teacher. We chatted with her and also the volunteer firefighters, and with some of the neighbors who stopped to see if everyone was OK.

The State Patrol officer later explained to us that there were 6 accidents in the region called in within a period of 5 minutes, when our accident happened. One happened just about 9 miles further west from us on Highway 94, in the town of Yoder. That accident had injuries, and some of the firefighters who were with us then had to leave to respond to the other accident.

At a minimum, this is a reminder to take care to drive safely, especially with limiting conditions like the sun setting ahead.

Plishner Work Trip Report – August 24, 2019

By Gary Agranat

Participants: Ed Corn, Steve Plock, Gary Agranat.

Ed, Steve, and I traveled to our radio telescope site, leaving from the Ellicott Fire Department a little after 7:30 am. We encountered just a little fog on the way.

Steve worked primarily on troubleshooting the amplifier failure on the 60-foot antenna fiber optic feed. Steve found a power supply no longer functioned. He wrote me later, “Damaged parts have been ordered and will be replaced at the earliest convenience.”

The 60-foot antenna dish was rotated so that Steve could access the feed from the service tower.

Ed Corn and I worked on assembling the 3-element tri-band Yagi antenna from Myron Babcock, and then the ham radio tower by the bunker, on which the Yagi antenna will go.  We measured and reassembled the three Yagi antenna elements and the boom support for them.  We’ll wait to combine those until we are ready to attach the antenna to a mast and on to the tower.  The antenna will operate on the ham 10, 15, and 20 meter bands. We decided to set the lengths so that the antenna tunes best in the center portions of the bands.

Assembly of the three elements of the tri-band Yagi antenna and its supporting boom.

We assembled the tower components out to a length of 50 feet, including the top that will hold the rotor. The tower is now designed and built to rotate from a pivot point next to the existing tower that had been started earlier.  Ed climbed that original tower to install the pulley; the pulley leverages and pulls up the 50-foot tower by rotation at the pivot.  We tested lifting the 50 foot tower with the hand crank winch that I think came from Steve.  The design works.  We eventually will need to take down the mast that supports the 80 and 160 meter dipole antennas, to complete the tower build-out.  We plan to re-attaching those antennas to the tower itself, when we are ready to complete the tower.  Ed has already fabricated two standoffs that will attach to the sides of the tower, and centrally support the dipole antennas.

Ed from time to time went to help Steve. And Steve once in a while came to help with the tower assembly.

The base of the new antenna tower pivots next to the already existing support tower. The rotating winch on the support tower will pull the antenna tower and lift it up or down.
On each of the three connecting tubes, on each of the tower elements, a set of two screws each were bolted to fasten the connections.
Ed Corn attached a pulley (fabricated before) to the support tower.
Three of the 10-foot antenna tower sections connected, and connected with the base pivot. The cable from the winch has been threaded through the pulley on the support tower above, and connected to about the 20-foot point on the antenna tower. The pipe mast visible in the photo is the center support for the existing 80 and 160 meter dipole antennas. The new antenna tower, besides supporting the directional antennas at top, will replace that mast and support those dipoles.
We tested rotating up the antenna tower with three 10-foot sections assembled. After Ed verified that the placement of the pulley was good, he securely fastened it.
The winch with cable installed, used to lift and lower the antenna tower for service. The handle crank is geared. The lock pin enables free movement, movement in one direction, and locking.
The top section of the tower, ready to be attached.
Steve helped Ed and I complete the final assembly of the tower.

We had a lunch break together in the bunker. I brought a small coffee maker and brewed coffee for Ed and me.

The weather was good, considering the heat we’ve been having lately.  High cirrostratus and mid level clouds from storms in the distance covered us for the afternoon, and kept the heat and sunshine comfortable.  We saw rain showers in the far distance, but those never came close enough to bother us. The bunker thermometer read 75 F, and outdoors was probably just a little warmer.

The Radio Jove phased dipole antenna array.
Bob Haggard’s steps provide much easier access to the Communications Trailer.
Sunflowers were blooming everywhere.
The bunker antennas in their configuration right now.

During a break I got on the air at the bunker station, and made 12 contacts for QSO parties that were running: 1 to Hawaii, 5 to Ohio, and 6 to Kansas, on CW and SSB, on 20 and 40 meters. I submitted our logs to those QSO parties later.

The 5 band vertical ham radio antenna, still in good working condition after the repair from the May storm. Photo taken in the late morning soon after we arrived. We used this to make our 12 ham radio contacts on the 20 and 40 meter bands.

For the team, Gary Agranat.

Radio Telescope Site Report, System 1 Team, August 17, 2019, by Glenn Davis

Here is a quick site trip report on the work the System 1 team (Phil Gage, Lewis Putnam, Dave Molter and Glenn Davis) completed at the Haswell Site yesterday (8/17/2019):

  1. We installed Version 4.0 of the System 1 software. This version includes a major new capability that supports manual tracking of astronomical objects. I would like to demonstrate this capability at the next Science or Engineering meeting.
  2. Version 4 included a software update to fix the Elevation Axis Bounce Issue (Erroneous Elevation Axis Status) that was identified earlier this summer and has been investigated for several years. The problem was related to the Elevation Axis Integrity Instruments 232M200 I/O module. Due to a board related hardware problem, the I/O board was always reporting bit 2 of the encoder position data as “stuck” on (1) which would create erroneous Elevation encoder data. The fix required both a hardware and software modification. The hardware modification included moving the bit 2 pin to an unused position on the connector to the I/O module (see #3) then provide a software fix that would read data from this new bit position and re-incorporate the bit data back into the Elevation encoder position data – bypassing the bad bit. This hardware/software solution has fixed the problem. The Elevation Axis is now providing the correct encoder positions through it’s range of motion and the “bouncing” has been eliminated.
  3. Dave Molter moved and soldered the “bad” Elevation Axis hardware pin to support the software modification that fixes the Elevation Axis Bounce issue.
  4. Collected Voltage to Rate information for both axis – data below:
Voltage (V) Azimuth Rates (Degs/Sec) Notes
0.00 0.00 Minimum Potentiometer Setting
0.20 0.04
0.39 0.08
0.50 0.11 Normal Potentiometer Setting
0.75 0.17
1.50 0.33
Voltage (V) Elevation Rates (Degs/Sec) Notes
0.05 0.06 Minimum Potentiometer Setting
0.17 0.07
0.35 0.08
0.75 0.11
1.52 0.15 Normal Potentiometer Setting
3.72 0.30
4.24 0.34
5.00 0.42

Please note: We were unable to produce zero rates on the elevation axis – even with the potentiometer turn all the way down.

Additionally, though we believe we returned the potentiometers back to their normal positions, whoever returns to the site for the next data collection, please ensure the potentiometers are at their normal positions before use.

Glenn Davis

Plishner Antenna Site Work Trip Reports for July 10 & 20, 2019

By Ed Corn

Trip Report for July 10

My wife and I spent the day at the site cleaning up the last of the electric basic infrastructure build out. That portion is complete with the following items completed.

  • Basic plug ins complete including a GFI plug near the sink and one in the bathroom for portable heater.
  • A pre wire and extra switch in bathroom for future ex-host fan and an electric water heater for shower and kitchen sink.
  • Box and wiring for sewer pump when that project starts.
  • Wall switch and permanent light in sleeping area.
  • The tunnel lights now have a control switch at both ends.
  • 240 volt plugins for amplifiers at the Amateur operating position.
  • The sub main electric panel in the battery room is complete and the main panel has the trim cover installed.

There will be extra plugs and services  that will be needed in the future but basic build out is complete.

* *

Scheduled Maintenance Trip Report for July 20

Steve and I went down Friday the 19th. We met Paul Berge at the house in Haswell. Paul and his wife came down Thursday and stayed over Thursday and Friday nights. Steve and I stayed in the bunker Friday night.

Paul worked on finishing installing the control wiring in the pedestal in the conduit for mechanical protection, and he installed heavy duty override switches in the override panel in the comm trailer. He also gathered information for some updates on the control wiring. He will be working on the updates at his home computer.

Steve worked on the fiber link from the feed point to the comm trailer. The wind came up Saturday so Steve will complete work later as the wind was a safety issue trying to work up at the feed point. Steve did say the az/el readout worked after cycling power.

I have the two 30 amp plug-in circuits at the old generator building completed to give us 2 more RV parking spots with heavy enough power to run 1 air conditioner in each RV. Just for information to turn lights on in the generator building you will have to turn the circuit breakers on in the distribution panel in the middle  of the North wall.

Plishner Site Work Trip Report for June 14-15, 2019

DSES Plishner Site Trip Report 6-14-2019
By: Bill Miller, Bob Haggart. Photos by Bob Haggart.

Location: Plishner Radio and Space Science Center, Haswell, Co.
Attendance: Steve Plock, Rich Russel, Jonathon Ayers, Floyd Glick, Bob Haggart, Bill Miller

Accuracy: This is only a summary of my work on Friday and Bob Haggart trip from his report for Saturday and you should add your own and correct anything I missed. WKM.

Bill Miller’s Work Trip Report, Friday, June 14th
Bill was the first to arrive at the site about 10:15 on Friday 6/14 and started by opening the trailer and removing the exhaust fan cover. He lubricated and reattaching the fan wires, started the air conditioners, swept the Comm. trailer floor and removed the mud left from the last visit.
Steve came in shortly after and he and Bill went to the top of the tower to inspect the Liquid-tight conduit that Steve had previously installed for the elevation position synchro wiring.

Jonathon Ayers came in and assisted Bill to hook up the wiring to the synchros on the elevation axis in the top deck.

Bill then got some assistance from Floyd Glick while hooking up the wiring in the control deck of the dish pedestal. Thank you to Jonathon and Floyd.
The goal was to attach the Elevation position synchro encoders to the synchro panel in the Comm. trailer. This would match to connections of the Azimuth synchros previously installed. It would complete the synchro dish position indicator system which is an accurate minimal tech backup dish positioning system that needs no computer.

Bill was under a tight schedule as Rich had a pulsar observation planned to start at 3:30. Bill tested the system and it worked initially but then started tripping the ground fault interrupter on the synchro panel within a few minutes indicating that the insulation or electrical clearance of the elevation connections was breaking down somewhere in the path. Because this circuit is 120VAC, the ground fault interrupter is critical to safe the system with the many intermediate connections and it did its job. (Caution) Bill unplugged the synchro panel from AC and it should be left unplugged until we have a chance to trace down the fault in the elevation wiring. It is most likely in the old terminal box in the control deck, moisture in the system or hasty wiring in the elevation axis Encoder box. I also believe that the synchros in the elevation axis box are either bad or incompatible and should be changed out and matched to those in the trailer synchro panel. Ed Johnson has a box of synchros from the bunker.

Bill had to leave about 4:00PM while Rich, Floyd and Steve stayed to make their Pulsar observation. This seemed to be going well but the large storm was brewing in the area and I suspect they had to abandon the site that evening.

From Bob Haggard’s Work Trip Report. Saturday, June 15th
Arrived at the DSES site 8:35am. Opened gate, opened the bunker to retrieve keys. Noticed the dish was setting at about 45 degrees. Opened the Ops trailer and the battery box for 110V AC power. Mounted the solar powered, dusk to dawn, LED porch light. Removed the camera and the broken rear trailer window. Installed the clear window and camera right side up. (there you go Rich) The molding to hold the window in was rotten, have to make 4 new ones. The putty was too old to be used, will need more on next trip.

Removed two folding chairs from battery box and stored them in the OPs trailer under the table next to the filing cabinet. Stored the donated table saw and stand in the battery box. Picked up all unused unwanted lumber (there you go Steve)

Secured the battery box and the Ops trailer. Returned the keys to the desk and secured the bunker and gate. Secured the main gate and departed at 2:45.

No one else showed up for this work day.

The weather was perfect, a mild breeze, just enough to keep you cool while working in the hot sun.

 

Plishner Site Work Trip Report for May 18, 2019

(Editor’s Note: This is Ed Corn’s report of our work at the Plishner radio telescope site during the weekend of May 18, 2019 – Gary, WA2JQZ)


I arrived about 9:30 AM and proceeded to the generator shed to install breakers and to survey the conduit route for 2 extra camper hook ups. The breaker box is ready. I will run conduit and wiring during another trip prior to the open house.


Steve Plock arrived shortly there after. We traveled separately so Steve could stay over with Paul Berge, as I have a graduation to attend on Sunday.
We looked at the ham radio tower project. All the hardware is on site but tower climbing is out for most of us. Steve decided we will assemble the tower on the ground, and tip it up with a winch at a later trip. We need a few extra parts to do this which are easily obtained or fabricated. Gary Agranat arrived and went to work on the vertical antenna. The vertical was damaged during the blizzard storm several weeks ago. He has a list of all needed parts for fixing on the next trip.


Steve moved the dish to the work stand and checked the control voltage for the feed to the preamps, and adjusted for voltage drop in the line from the communications trailer.


Steve and Gary then worked on tuning the 16o meter and 80 meter wire antennas. (Gary added: We trimmed the lengths to retune the antennas to about the center of the ham bands. The 160 meter antenna was tuned to 1.9 MHz, with a best SWR of 1.7:1. The 80 meter antenna was tuned with an SWR of 1:1 from 3.8 to 3.9 MHz. Before the tuning, each antenna was slightly long, which therefore gave better performance at the low ends of the bands. The retuning enabled better resonance in the phone portion of the bands, where several members like to participate in nets.)


I moved into the bunker and pulled wire for the sub main panel in the battery room, in preparation for the hot water heater for the sink and shower and the sewer pump system. The sub main is complete, ready for extension of the conduit runs on a future trip.


Paul arrived late afternoon and stayed the weekend with several items he wanted to work on.


Ed KC0TBE

Photos by Gary

Plishner 60-foot antenna

Bob Haggart’s work building a new porch and stairway for the communications trailer

Bob Haggart N0CTV is working on building a new stairway and porch to the communications trailer at the radio telescope site.  He started the work at home after taking measurements. Today he traveled to the site to continue the work.  With him were his grandson Allen and Allen’s friend Ben. Bob writes:

“We arrived at 11 AM. Worked on the porch and covered the fan with 24″ X 24″ plywood. Ran out of time but did get the porch assembled and painted inside and out. The hand railing is only temporary and will finish next work day on the 17th.”

Bob’s work is replacing a small simple set of metal steps that has given us access to the communications trailer.

The original set of steps to the communications trailer. Bob’s new porch and stairway is replacing this.

The new porch and stairway provide a great improvement.

Bobs has built this new porch and stairway. It is larger, sturdier, and gives much better support. The handrail is temporary. The permanent handrail is planned to be installed on the next group work trip on Nov. 17.

Bob Haggard N0CTV, standing with his work.

Thanks to Bob for all this work, and for improving the access to the communications trailer.

Plishner Site Report for the Weekend of October 19-21, 2018

This is a summary of our activities at the Plishner radio telescope site during the third week of October 2018.  Steve Plock, Ed Corn, and Gary Agranat contributed to this report.

Participants this weekend were Gary Agranat, Paul Berge, Tony Bigbee, Ed Corn, Hans Gaensbauer, Dave Molter, Steve Plock, and Rich Russel.

Our plan for the rest of the year is to work at the site during the third weekend of each month.  The Friday evening is devoted to astronomical observing, and the rest of the weekend is then devoted primarily to infrastructure and equipment work.

60-foot Antenna Observing, by Gary Agranat, WA2JQZ

On Friday afternoon and evening Rich, Gary, and Paul did 1420 MHz neutral hydrogen observing with the 60-foot antenna.  The primary observing goal was to take regular measurements of the hydrogen signal along the Milky Way galactic plane at 10 degree intervals, from the galactic center to about 110 degrees (a little more than the first quadrant).  The Doppler shift of the hydrogen was measured at each 10 degree point. From that, Rich later used some basic geometry to derive a velocity and distance from the galactic center for each measurement.  A second goal was to observe several known, strong galactic radio sources that could be used in the future for calibration of our observations, and also to see if we are capable of observing those sources in a consistent way (without unknown biases).  A third goal was to observe additional galactic sources as targets of opportunity, to see how well we do, and to also see what problems we hit.

Galactic plane observing started at about 5 pm local time, when the galactic center in Sagitarius had risen high enough in the sky for us to observe. The galactic plane and most of the other observing were done with the 60 foot antenna pointed along the meridian (180 degrees azimuth to the south and zero degrees to the north), in order to eliminate the Earth’s rotational motion in the Doppler shift measurements.  We observed until about 10:30 pm, when the team was then quite tired. To warm us up during the evening, we made a batch of hot apple cider.

Details of the observations and results were discussed at the science meeting on Monday October 22nd, and those will be covered in a separate post.

– Gary WA2JQZ

60 foot dish antenna on Friday late afternoon, as the galactic plane observations started.

 

We’ll continue with the discussion of the weekend infrastructure work.

Saturday Infrastructure Work by Ed Corn, KC0TBE

Our first order of business was to re-service the toilet and spare in the outhouse. They now both have RV antifreeze for winter. Next installed was a portable heater for winter operations and I labeled all the breakers in the out house. I then labeled the doors with instructions for emergency exit and the safety pin for privacy at the main door.

With the help of Gary, Hans, and Paul we have the first 3 tower sections in place at the bunker, along with the first set of guy wires. [More about the tower below.]

-73’s Ed KC0TBE

DSES Site Work Report by Steve Plock KL7IZW, DSES President

Paul Berge worked on Friday, Saturday and Sunday. Because he travels  from Lyons, Co. he prefers to maximize his efforts each visit. Also the weather window for the year is closing. I attempt to support his efforts as best as I can. Paul provided support for Rich Russel’s data acquisition which included galactic Doppler measurements. The team  knocked  off before midnight.  Results have already been detailed in the  Science meeting on 22nd of October.

On Saturday Ed installed a heater in the outhouse, winterized the RV toilets, and labeled the outhouse breakers.

During Saturday afternoon Hans, Ed, Paul, Steve and Gary all worked together to erect the new communications tower. The first set of guys were finished  at 23 ft. by Ed Corn doing all the climbing.   The majority of the rest of Saturday myself  and Paul spent evaluating the elevation limit switch operation, including testing complete functionality with fault clearing via the built in override capability.

Later that day, Tony Bigbee showed up, and Paul and Steve supported subsequent  hydrogen observations using the RASDR4 receiver.

The majority of Sunday was consumed by lubrication of the dish and adjustment of the azimuth drive chain. I also installed the conduit in the elevation bulkhead so that Bill Miller can complete his synchro  wiring project.

Sunday Dave Molter worked into the night using the 500W floodlights and mixed over 1000lbs of concrete to try to prevent continued erosion in the ramp area.  A big thanks to all who participated in  this cooperative effort.

– Submitted by:  Steve Plock,   President DSES

Photos by Gary, from Friday and Saturday:

Position of the 60-foot antenna as it is pointed due south, at 180 degrees azimuth along the meridian.

The Moon with the 60-foot antenna.

View from the base of the dish antenna, looking towards Haswell.

Haswell as the sun set Friday evening.

Pikes Peak and Cheyenne Mountain were visible on the horizon, about a hundred miles to the west-northwest.

Work Saturday morning at the outhouse.

Work at the outhouse, including labeling.

Hans helping Ed unload tower sections and a jin-pole, for building up the ham radio communications tower at the bunker.

The first section of the tower had already been installed during the last work trip. Here Ed is safely secured to the tower after the second section has been hoisted with the jin-pole, which is also temporarily securely attached to the tower. He is fastening the bolts of the second section on to the top ends of the first section. He did this again with the third section.

Ed fastening the bolts of the second tower section on to the top of the first.

The team standing ready as Ed works on the tower. Hans is standing by the third tower section.

The tower at left with the third section up. A 6-meter delta loop antenna was hung from the tower to the doghouse. Stainless steel guy wires were also extended from the third section, per tower specifications.

Hans, Paul, and Gary installed supports for the guy cables, at one-third intervals around the tower.

Hans and Paul securing one of the guy wires at the ground support.

Configuration of the tower with 3 sections, until work resumes next time. The current plan is to install one more section with a rotator. The rotator shaft will have at least a triband HF yagi antenna and a 6 meter directional antenna for meteor scatter. Also, small horizonal supports will be added to support the 80 and 160 meter dipoles, currently supported at that position with a pole.