Fiber Cable Installation

These are photos, shared by Steve Plock, from the installation of the 100 meter fiber optic cable during the first week of March. The new cable runs from the antenna feed to the com trailer, and replaces a coax cable. A 50-foot lift was rented, to run the cable to the antenna feed. Ed Corn worked from the lift bucket.

The installation was originally scheduled for Monday March 5th, but the winds were too strong. The winds were not as strong the next day, though still a challenge, and they did the installation then.

The fiber optic cable enables a higher data rate, and also eliminates a significant source of noise.

Skip Crilly, Monday March 5, 2018.
Ed Corn working from the bucket. Tuesday March 6, 2018.
Ed working from the bucket, with Floyd Glick and Bill Miller watching on the ground. Tuesday March 6, 2018. Also present were Glenn Davis and Paul Berge.

 

Plishner Site Report March 17, 2018, and other Updates

By Gary Agranat, March 27, 2018.
Updated March 29, 2018 0200 GMT: 1) Skip Crilly’s slides were updated, and 2) the supernova remnant detected was NRAO 5690.

On Saturday March 17, four of us were at the Plishner antenna site: Steve Plock, Ed Corn, David Molter, and I (Gary Agranat).

And before I say anything more, I want to point out that the site has had much activity over the past few months. Full commercial power was installed and the site now operates using that. A number of simultaneous observing runs were made with Skip Crilly at the 40 foot dish of Greenbank Observatory in West Virginia, 1257 miles distant. More about that later.

Plus, a number of equipment upgrades to the site were made. Many of those enable the joint observations, yet also enhance our ability for observations on our own. For example, a few weeks ago a 100 meter long fiber optic cable was installed from the antenna feed (at the focus of the dish) to the receiver at the communications trailer. In order to install it, a 50-foot lift was rented. However, the installation had to be delayed a day because the originally planned day was too windy. Replacing the coax with fiber optic cable eliminates a significant source of electrical noise to the receiver. This is very important for radio astronomy observing.

Effort has been ongoing as well to troubleshoot and make work our two independent antenna pointing control systems. One system was designed by Glenn Davis and David Molter, the other by Ray Uberbecken and Ed Johnson. Both seem to be good workable solutions, and we will have one back up the other. An ongoing problem we have been troubleshooting is electrical noise.

Meanwhile, Rich Russel and Skip Crilly traveled to the Society of Amateur Radio Astronomers Western Conference at Stanford University in California, to give talks based on papers they wrote. More detailed information about these other activities are already, or will be, posted on our website.  And so we have been very busy, and doing much. Today’s activities are a moment in a bigger story.

* *

This is our connection to commercial power at the entrance to our site. New utility poles and a power line were erected, which connect to an existing power line about a mile to the north.

On this trip, Ed brought an additional roll of fencing. David Molter and I (Gary) then completed fencing the periphery of the bunker entrance ramp. The bunker when it was originally built in the 1950s had a fence, but it deteriorated away since. Without a fence, tumbleweed accumulate in the ramp when the winds are strong enough. And it is a chronic, time consuming task to clear our the entrance. The fence is a worthwhile accomplishment.

David Molter completing the last section of fence.
David Molter completing the last section of fence.

The last part of the fencing job was to create a moveable gate across the ramp entrance. Ed, Steve and David created an improvised gate with the fencing, and with spare re-bars (steel bars for reinforcing concrete), and hooks.

A used Hustler 5-BTV vertical ham radio antenna was donated to us. We plan to erect it near the bunker. Its coverage is the 10, 15, 20, 40, and 80 ham radio bands. I inspected the parts, and found we just needed a few “spider” radial parts for near the top of the antenna, to replace worn or missing parts. As of this writing, David got us replacement parts, and we are ready for the next steps for installation. An existing pipe in the ground might be used to mount it, or we may put in a new one. Given the wind conditions, we will guy the antenna with non-conducting cable.

Ed has been installing an internal phone system on the site. Phones are being installed at the pedestal, com trailer, and bunker. Dialing a number will ring an individual phone. On future trips, Ed will also install a VHF radio, connected to the phone system, so that one can “call in” from outside using the ham VHF 2 meter band.

David Molter
Ed Corn

**

Steve and David worked on the pointing control system. David wrote these details for us:

For the elevation/azimuth work that I did last weekend:  I used a bubble level to set a horizontal line, then zeroed the bubble level/inclinometer that I brought. Steve and I moved the mount to as close to 0 degrees elevation using the vertical part of the inclinometer by lining up the edges of the dish and sighting across them until they showed vertical from where we were standing on the ground.  The readout on the computer was minus 0.1 degree. I then took the digital inclinometer and zeroed it on the same bubble level. I took it up to the back of the dish and measured the elevation axles. The left axle measured minus 0.1  degrees and the right axle measured plus 0.4 degrees.  I then measured the horizontal beam on the left side as you are looking out the dish it measured 0.1 degree. I can’t remember if it was plus or minus. The same beam on the right side measured minus 0.7 degrees.  Steve then rotated the dish to point to the Haswell grain elevator He moved the dish until the feedhorn blocked the view of the elevator as I was looking through the bottom of the reflector.  I then checked the seam of the azimuth electronics box and it was lined up with the tower part of the elevator. Steve knows what the reading was. I didn’t observe the elevation lights when the dish was moving. I did observe that the 3/4 inch ‘liquid tight’ sealable conduit was secure at the elevation electronics box, and it ends about 3 feet into the tube where the wires go into the upper mount level.

I then started helping Ed troubleshoot the phone system.

Before I did the elevation observations, Gary and I put up the fence that Ed had brought down. We completed the run along the North East side to the end of the ramp. After lunch, Ed, Gary, Steve and I  built (designed, created, hodge podged, jury rigged, slapped together) a gate out of the same fence material. Now the ramp is surrounded by a ring of steel (fence that is).

**

During the day we had two visitors from Las Animas: Sharon Branch and her friend Cheri Martinson. Sharon is a member who joined last November. I gave them a nice tour, with some background of the history and science. Steve then took them up the dish antenna. Cheri later wrote us a delightful letter, and she became a member too.

Views of neighbor farm fields:

Late in the afternoon two photographers came who had arranged to work overnight, in order to photograph the dish with starry background: Mike Cunningham, who has become a member, and a friend.

**

For the past few months we have been doing a series of joint observing runs with Skip Crilly, who uses the 40 foot dish antenna at the Greenbank Observatory in West Virginia. These observations are for SETI (Search for Extra Terrestrial Intelligence). However, a test observation also detected the supernova remnant NRAO 5690. The detection and measurement of NRAO 5690 is probably our first real confirmed detection of an astronomical object with the Plishner 60 foot dish antenna. These joint observations are the subject of Skip’s talk at the SARA Western Conference at Stanford.

Now that he has given the talk, we have posted a recent revision of his slides on our Publications Page on our website, in the Science Section. See: “Geographically-spaced Synchronized Signal Detection System”, by Skip Crilly.

The next set of joint observations are scheduled for April 9. Several members will be at the site to carry out observing, and to also continue site work in between observing runs (which last about 30 minutes).

At this week’s DSES Science meeting, Rich Russel gave us details about the SARA Western Conference, including his paper. Rich also discussed bringing the Jupiter-Io experiment “Radio Jove” back online, now that Jupiter is placed well again for observing. And he discussed a week-long “Synthesis Imaging Workshop” (on radio telescope data imaging) that he will be attending. The dates are May 16-23, and the location is near the Very Large Array (VLA) in New Mexico. He also plans to attend the main SARA conference in Greenbank, West Virginia this summer.

***

Some more news:

  1. Last week the votes for the 2018 DSES Board election were counted. The Board members elected are: Rich Russel, Steve Plock, Myron Babcock, and Gary Agranat. Thanks to Lauren Libby and Bob Sayers who also ran.
  2. With the Board election completed, the Annual membership meeting is now being planned. The scheduled date is April 14, probably at 2 PM. A location is being finalized now.

The DSES Secretary should be sending formal announcements soon.

73,
Gary
WA2JQZ

 

Plishner Site Report – January 25 & 26, 2018

Steve and I arrived at the site about 9:40 AM Thursday. We energized the main line up to the bunker. We than made the necessary voltage checks for each of the branch feeders and energized the entire distribution system. The Plishner site is now on grid power.

All of the battery packs and inverters are still in service. Reminder that any light or plug  sprayed with red paint is an inverter outlet, any plug or light with no paint on the box is grid power. Be sure to turn everything OFF before leaving the site.

Steve worked with Skip Crilly at Greenbank by phone to turn up equipment and point the dish for the data observations. Steve had everything running for the first observation and continued running until 12:50 PM Friday the 26th. We shut down at that time and removed the equipment for shipment back to Skip for maintenance and upgrade. Steve will ship after returning back. All indications are a successful data run.

Between checking equipment, we added wire to the 160M dipole at the bunker. It is better but needs some extra work. Also filled the wire trench in front of the concrete slab at the top end of the ramp to allow driving on to the slab and not having to jump the trench going in to and out of the bunker. This leaves about 500 feet of trench to fill; We will need some help with this in February.

I also installed a dedicated outlet in the generator shed to feed the LAN switch that is necessary to provide cat 5 Ethernet from the Comm Trailer to the bunker. The last item we covered was moving the WIFI hot spot to the bunker. There is now wireless internet in the bunker. We did not have the manual for the converter from wireless to cat 5 with us to configure the unit. This will be completed next trip to provide internet on cat 5 cable end to end at Plishner. This relocate removed the RF from the hot spot in the Comm Trailer during observation times.

Note: The sump pump in the battery room is on grid power and the front entry way sump pump is on inverter. I will change over to grid power after a wiring change. This will be first order of business next trip.

We secured the site and left about 1:30 PM Friday.

Ed and Steve

DSES Commercial Power Installation Update

Posted by Myron Babcock, DSES Treasurer.  Photos by Steve Plock, DSES Vice President.

Thanks to Skip Crilly for his $37K donation and to Steve Plock and Ed Corn for leading this effort to fulfill the dream of connecting the DSES Plishner Site to the AC Power Grid. Steve reported on Saturday December 9 that approximately 22 power poles, almost 5000 feet of wire, and a 25KVA transformer were installed last week. The Colorado Southeast Power Association worked 5 days in accomplishing this task. Saturday December 9, Steve Plock, Ed Corn, and Glenn Davis spent the day assisting local resident, Mark Nelson, from Haswell, CO in the trenching of approximately 600 feet of ground from the transformer pole area to the Southwest corner of the bunker area. Number 4/0 3 wire URD/with reduced neutral wire is now in the trench and once inspected by a Southeast Power Association representative the trench will be filled back in. Ed Corn has the necessary supplies for final connection to the bunker power panel. Once completed DSES will have 220 VAC 100 amp service in the communications trailer and 220 VAC 100 amp service in the bunker. Currently the plan is for the existing 30+KW propane generator to be disconnected. A decision will be made at a later date as to the disposition of this generator. Existing solar panels and batteries will continue to be used until such time as it is deemed the continuing expense out ways its usefulness.

 

Looking North along Kiowa County Road 20. The white structure in the background is the 200 foot tall grain elevator 5 miles north in Haswell, CO. The electric meter will be mounted on the nearest pole next to the fence.
The trenching operation starting from the southwest corner of the bunker area. The structure at the starting point of the trenching operation is the “dog house” emergency bunker entry/exit over the recently constructed spiral staircase. Next to this structure is a 40 foot telescoping mast supporting the 160 & 80 meter dipole antennas.

October 29, 2017 DSES Plishner Site Work Trip Report

Report written by Bill Miller, DSES Secretary.

Location and Time: On Sunday, Oct 29th Ed Johnson and Bill Miller made a trip to the site to reinstall and tune the computer for the System 2 dish controller.

Attendance: Ed Johnson, Bill Miller

Site Activities:
A. Bill arrived on site by 9:00am, unlocked the facilities and fired up the generator. Ed arrived a little later and brought in the bench computer on which he had repaired the operating system corrupted by a MS update from the last trip. We immediately hooked up the computer to the controller interface in the pedestal control deck via the Ethernet LAN interface and got to work. Several items in the software needed to be corrected.

B. Ed added a Start and Stop ramp subroutine to the motor drive software to prevent the system from abruptly starting and stopping the drive at high speed. This generates a stepping ramp function to start the motors slowly and speed up to the desired speed and then slow down in a similar fashion to stop. It greatly helps to reduce the stress on the system and should reduce over currents from popping the 3 Amp breakers on the drives. Some amount of iterative tuning of this was needed to get this to work just right.

C. A problem was seen when the computer would pause and stop communicating with the interface about every 10 seconds. This is a critical fault which would render any closed loop control unstable or ineffective. We attempted to find the source of this problem. We traced and substituted the LAN switches, CAT5 wires and connections and eliminated this as a cause. We turned off as many processes in the machine that could interrupt the system as possible. Ed found that by unloading the MS Visual Studio program that the interrupts occurred about half as frequently but they still occurred. We finally concluded that the PC was just not fast enough to perform the control function with all of the other MS programs and housekeeping functions and this was causing it to hesitate. Ed decided to donate another laptop he has with considerably more speed for this function and will ready that for the next trip. Bill will pick it up at Ed’s in Limon if Ed can’t make the trip. In the mean time we left the bench computer in place to control the dish pointing.

D. While Ed was modifying the software and testing the movement, Bill monitored the result from the pedestal control deck and also spent some time mapping out about half of the controller box. He will finish that on the next trip and transfer the diagrams to schematic capture for documentation.

Observations: Some important observations are as follows:
A.  It was found that there is a fault in the elevation optical encoder. At several particular positions of the elevation the encoder would jump a number of degrees in value. For instance at 44 deg of elevation it would suddenly jump to 50 deg. So the 6th significant bit appeared to be faulty. These errors always occurred at the same positions indicating a fault in the encoder and not the electronics attached. This could be contamination or a scratch on the optical device. Since we use only half of the encoder for the +0 to 180 elevation position sensing it might be possible to realign the encoder 180 deg off and use the other half of the bits if no errors are seen there. If not the encoder will have to be repaired or replaced. This problem was not seen on the Azimuth encoder but we were not looking for it. A means of testing the encoders for such a defect would be a handy utility in the software that we should add.

B.  Even with the start/stop ramp function and driving the dish at a relatively slow speed we still had the 3 amp breakers tripping, sometimes in the middle of a continuous movement when we were not starting or stopping. We need to measure the currents in these breakers and determine the root cause whether an overload, controller fault, worn or miss-sized breakers. This is a real nuisance when trying to move the dish and must be corrected before computer control can be effective.

C. Bill stayed in the tower communicating with Ed on the radio to position the dish from the previous ~ 45 deg elevation for 40 Eridani observation to the parked 90deg (birdbath) and 315 deg azimuth position. This 315 deg azimuth position is the optimum service setting to allow access to the upper deck and dish though the service portal. It is also the best position to allow the feed point to be driven in elevation only to the -0 or 180 deg position to place the feed on the service tower.

Shut Down:
We had to wrap up the work by about 3pm to travel to other commitments. After setting the dish to the parked position Bill shut down the lights, locked all of the doors, returned the keys and shut down the generator using the original procedure of turning off the main gas valve. This may not be required anymore but as yet we haven’t officially changed the procedure and it is the safest condition if we are not on site for a while.

That concludes the minutes from our Plishner site work trip of October 29th, 2017

73, and keep looking up! 
Bill Miller
KC0FHN
DSES Secretary
Email: mountain_son[a]comcast.net
Snail Mail to our new Colorado Springs Address at:
Deep Space Exploration Society
4164 Austin Bluffs Pkwy. #562
Colorado Springs, CO 80918-2928

Plishner site work trip October 21, 2017

During the work trip on October 21, 2017, a single-band 1420 MHz circular polarized feed was installed. This feed was built by Steve Plock KL7IZW.

The antenna was set with an azimuth of 149.6° , and with an elevation 39.2° above the horizon.  This allows the antenna to drift scan the sky along an arc, as the Earth rotates, at Declination -7.5° (celestial latitude).

This scan was designed to pass across the triple star system 40 Eridani, at about 0200 local time. This was a joint SETI project with Skip Crilly to make simultaneous measurements together with the Green Bank Observatory 40 foot radio telescope in West Virginia. The two sites are at about the same latitude, at a distance of about 1300 miles.  Joint observations were scheduled for the early mornings of October 26, and October 29.

The specific target of interest was 40 Eridani A, which is at a distance of 16.4 light years.  Eridani A has a habitable zone around it for an orbit calculated to take 223.   The frequency spectrum of 1405 to 1445 MHz is continually sampled, in order to look for “triplets” signals.  Simultaneous observing from two distant sites would rule out that any signals detected at both sites cannot be from local terrestrial sources.

The technique of “Drift Scan” is just keeping the antenna pointed in one  fixed direction, while the sky passes overhead as the Earth turns. Rather than track a particular object, the sky is passively scanned, as the sky “drifts” across.

Also continuing:

  • Total power measurement @ 1428 MHz, beam size 2°
  • Neutral hydrogen spectral line measurement
Skip Crilly setting computers to record data for his SETI triplet study of 40 Eridani, at the DSES radio telescope site in Haswell. The project will simultaneously make the same measurements with the 40-foot radio telescope at the National Radio Astronomy Observatory in Greenbank, WV.
Skip’s antenna analyzer, in use.
The 60 foot antenna set to drift scan for 40 Eridani, as the sun set with a crescent moon.

Also on this trip, Gary Agranat WA2JQZ operated the ham station from the bunker, to participate in the annual Boy Scouts of America Jamboree On The Air (JOTA). Ops were on 20 meters, using the bunker’s 160 meter dipole. Two JOTA stations were contacted in California, W1AW/6 and N6B.  Other JOTA stations around the US and also Mexico were heard, but conversations among them were already well in progress, and so we didn’t interfere with those. Attempts were made to listen for the JOTA station in Colorado Springs, operated by Dave Molter AD0QD, but it was not heard.  In between JOTA ops, the club also participated in the New York State QSO Party, on CW and SSB, with 19 contacts.  And 9 contacts were made with JT65.  The longest distance JT65 contact was to Spain EC2ATM, and with SSB to 9A3XV in Croatia.

Skip Crilly used his antenna analyzer to check both the 160 and 80 meter dipoles located at the bunker.  He verified that most of the lower part of the 20 meter band was usable, and the 17 meter band was as well, but many of the other ham bands were not with the current length of the antenna.  Ed Corn KC0TBE later also used his antenna analyzer to check the antennas and feeds.  And he checked the amplifier.

Ed Corn also placed the two sump pumps on separate power inverter feeds.  That ensured that each pump can start independently if both are needed simultaneously.

Ed Corn KC0TBE using his antenna analyzer.
The bunker ham station set up.

Paul Berge, who was active several years ago, drove to the site from the Denver area. He discussed past and current projects with the team. Paul Berge, Steve Plock, and Skip Crilly stayed at Haswell overnight, to continue work the next day. Overnight the sky was clear, with the Milky Way clearly visible. The Orionid Meteor Shower was in progress, and several other members of the team stayed past sunset to watch the night sky as well.

Also working at the site on this trip were Rich Russel ACoUB and Ed Schade KC0HCR.

Photos from Plishner radio telescope site work trip October 7, 2017

Main efforts on this work trip were:

  1. Testing by Ed Johnson, Ray Uberecken, and Bill Miller, of the system II dish motor controller and software.
  2. Checking ability of the the 1.2 – 1.4 GHz feed to receive.
  3. Completion of Phase 1 of the bunker ramp retaining wall, by Ed Corn and Steve Plock. The wall is now 8 blocks high.

Also during the day, Gary Agranat represented DSES at the community fair in town, the Haswell Bazaar.

For more details, see the 2017-10-09 DSES Technical Planning Meeting Minutes.

AD5MQ, Ray Uberecken AA0L and Bill Miller KC0FHN testing the System 2 pointing system. They also listened for 1.296 GHz and 430 MHz beacons to test reception.

More work on the new retaining wall for the bunker ramp, by Ed Corn KC0TBE and Steve Plock KL7IZW.

The condition of the remainder of the south side of the bunker ramp.

Site generator building and propane tank.
After testing the antenna pointing system, the 60 foot dish antenna was again pointed a few degrees north to scan for Cygnus A and for galactic neutral hydrogen.

2017-09-02 DSES Plishner Site Work Trip Report

Here is a summary from our work trip to the Plishner Radio Telescope site on Saturday September 2, 2017.  It includes many photos of what we did.  Highlights include:

  • Work started on rebuilding the bunker ramp retaining wall
  • Work on the control boxes which control the azimuth and elevation pointing of the 60 foot antenna
  • Maintenance and calibration of the Radio Jove and total power measurement instruments
  • Positioning the 60 foot antenna for detecting radio source Cygnus A during drift scan
  • Colorado ham radio QSO Party participation

The summary report was written by DSES Secretary Bill Miller.  The ham radio report was written by Gary Agranat.  Click the link to see the report in PDF.

2017-09-02 DSES Plishner Site Work Trip Report rev3

Photos from our site work trip July 23, 2017

These are photos taken during our work trip the Plishner radio telescope site on Sunday July 23, 2017. – Gary WA2JQZ

 

 

 

 

 

Ray Uberecken AA0L and Steve Plock KL7IZW reinstalled Ray’s 3-band antenna feed at the focus of the 60-foot dish. Bill Miller KC0FHN and Gary Agranat WA2JQZ  helped from the ground.

 

 

 

An all-day project today was the rebuilding of the “Radio Jove” phased dipole antenna. The first version had been constructed with PVC pipe masts, but that was collapsing. Dave Molter AD0QD redesigned a new antenna support system, using surplus stainless steel pipes, and adding springs and pulleys. Last autumn the bases for the poles had been already set with concrete. Today most of the team helped rebuild the antenna at one time or another. The placement of the structural support ropes was carefully rethought. Floyd Glick WD0CUJ fastened all the knots.  Here is the result.  This antenna system is used to monitor radio pulses emitted from Jupiter and its moon Io at 20 MHz.  These pulses are among the strongest astronomical signals observable.

 

Ed Corn KC0TBE contributed with much facilities work. Here he is installing a small solar panel to charge the 12 volt batteries at the generator.  With him is Floyd Glick WD0CUJ.

 

Ed Johnson AD5MQ walked around the 60 foot antenna with a UHF signal source.
Inside the communications trailer, Ray Uberecken AA0L monitored how the signal was received.
Ed Johnson AD5MQ
Ed Johnson AD5MQ
Bill Miller KC0FHN constructed a ventilation fan to the side of the communications trailer. The fan is self-powered by a solar electric panel. Its purpose is to help exhaust the hot air that builds up in the trailer during the summer season. It turns on automatically whenever the sun is out. Bill first cut a wood mounting frame to place on a window opening, to mount the fan.
Bill KC0FHN installing the fan at the side of the trailer.
Bill KC0FHN installing the fan at the side of the trailer.
Ed KC0TBE meanwhile installed a new air filter for the trailer, to help the air flow for Bill’s vent fan.
Inside view of the new trailer ventilator fan.
The new small solar panel on the roof is to power the ventilator fan.
The ventilator fan, installed by the end of the day.

 

The propane fuel tank for our generator.
Our generator shack.

 

 

 

DSES Plishner Work Trip Report July-02-2017

The following report was provided by Ed Corn and Steve Plock.  Special thanks to Gary Agranat for providing the pictures.

Myron Babcock
DSES Treasurer

 

 

Greetings all:

This is a summary of our trip to Plishner Sunday 7-2-2017. Steve, Dave, Bill,  Gary and my self made a very successful trip with a few exceptions.

Dave, Bill and Gary worked on the tumble weeds, cleaning all out of the ramp. I am positive they combined lost a bunch of weight (sweat down their backs) It was a bit warm. We all were involved in installing the chain link and construction safety fence around the perimeter of the ramp. We had enough fencing to do about ¾ of the perimeter. The rest will be completed the next trip down. This should take care of about 95% of the tumble weed problem.

Steve and I went to the comm. Trailer and re established the bunker battery monitor line. We discovered that Myron’s Hot Spot adapter has quit functioning. (DOA) I will get the unit back to Myron for exchange with his carrier. We need an agenda Item at the next engineering meeting to discuss the failure and preventative measures to prevent future failures.

Steve and I went to the generator tank and changed the wet leg valve. The excess flow check valve did check lock as designed so we did not have to depressurize the tank.

I corrected the wiring on the start/stop remote stations for the generator and Steve went to the bunker to help with the fencing.

After lunch we removed the feed and controller for the dish and Dave will deliver to Ray for modification.

I know I have forgotten some things the rest will have to fill in.

On the trip back Dave had a slow leak in a tire. Bill got him aired up and headed west. Steve and I headed home in my pick up. Just before Punkin Center I ran out of propane and switched fuels too late. This disabled my vehicle. So we put Steve in Bills van for the trip back to Ellicott and I called a favor from a friend who came down and recovered me. As of this writing the pick up is back on the road. Just too long of a day to make repairs on the road.

Submitted

Ed KC0TBE

* *

Steve Added:

Myself and Dave Molter removed the multiband feed from the dish and Dave Molter delivered it to Ray’s house along with the feed control panel which I removed from the comm trailer.

The original station clock has been put back near operating position in comm trailer. Bill Miller inflated tires on bunker transport wagon. I removed the hotspot from the comm. trailer and when Myron is given a replacement from his wireless provider I recommend that we re-install it in the bunker because there is a much better environmental conditions for it to operate. The main valve on the 1000 gal tank was successfully replaced by myself and Ed Corn and tank can be filled after leak test is performed. Ed will contact Haswell Propane this week to arrange pressure test and fill. Please distribute.

Thanks, Steve KL7IZW

* *

Bill added:

Additionally Steve and Ed loaded some of the old excess test gear and servers from the bunker onto Ed’s truck and sold them at the PPRAA ham fest the following Saturday. Bill brought back another one of the bad 6 volt deep cycle battery cores and will get the other from Ed to turn in for credit for two new batteries for the battery room on the comm. trailer.

Bill KC0FHN

 

The spiral staircase we constructed for the bunker, as a secondary/emergency exit, now being painted.