Plishner Radio Telescope Site Work Trip, July 20 -23, 2018

Trip report and photos by Gary Agranat and Bill Miller, with contributions from the rest of the team.

We traveled to and worked at the Plishner radio telescope site during the weekend of July 20 to 23, 2018. Attending were: Steve Plock, Ed Corn, Paul Berge, Bill Miller, Dave Molter, Gary Agranat, and Tony Bigbee. This is a summary of what we did:

– The site received several days of heavy rains during the previous week. The bunker sump pumps were overwhelmed and the bunker was flooded. Steve and Paul spent a number of hours on Friday and Saturday morning clearing out the water and cleaning up. Steve reported clearing at least 60 gallons of water. Dave later on Saturday also spent time removing water and cleaning. Paul cleaned up some more water on Monday morning.

– On Saturday morning Paul and Bill filled in the conduit trench for the synchros.

– Ed installed a conduit and the power cables from the pedestal to the outhouse. He also started to install the cables from the outhouse that will lead to the RV power risers and connections. Ed said he intends on the next site trip to put in breakers, extend the wires to the RV locations, and install the outlets there.

– Paul put in wiring to the limit switch system, for azimuth and elevation limits of the dish travel. Paul stayed over Sunday to complete more of this.

– Paul and Bill installed the synchro indicator panel and reinstalled the manual dish steering control panel in the rack, in the com trailer. The panels in the rack will still need to be moved down one U space, to accommodate Skip’s TM-4 timing control. The Spectrum Analyzer was moved over to the adjacent rack. Paul installed the limit switch control panel under the manual control panel in the rack. They redid the panel configuration so that all the panel controls have azimuth on the left and elevation on the right to match convention. Bill relabeled all of the control panels to provide a more organized presentation of the switch and knob functions.

– Bill brought out the System 2 dish controller and laptop. It had worked well on the bench at home, but at first didn’t work at the site. After some frustration he called Ed Johnson and they worked through the problem. The static IP address of the computer had to be set and then the system communicated and could be tested. Paul stayed in the tower control deck while Bill drove the dish from the comm. trailer. A fairly serious problem was found and Ed was consulted again by phone. The watch dog timer was apparently timing out and dropping the power to the motor drives about 3 times a second. Seeing this they immediately shut it down. Bill took the system home to do a modification on the VFD power enable relay and to trouble shoot the reason for the time out. Once fixed, he will bring it back for more testing. Bill informed Dave Molter of the problem and asked that he not repeat the same issue in the motor drive control circuits of System 1. Bill also provided Dave with a linear power supply and some parts to complete System 1 controller.

– Bill also installed the latch on the System 2 Controller and temporarily installed the DB25 switch boxes in the control deck so we can switch between systems for test and maintenance.

– Steve and Gary worked on installing the MFJ auto-tuner for the FT-897 ham transceiver in the bunker. They found that the tuner would not power up, although the manual indicated that it should have. There is an alternative way to directly power the tuner, but they didn’t have the proper wiring. Steve gave Gary a wire on Monday, which can be used to connect the tuner directly to the power supply (located lower on the bench below the rigs). Gary also brought the mini-manual for the FT-897. It is like a checklist, and is useful for quickly finding menu settings.

– Gary used Dave’s antenna analyzer to check the SWR across the ham bands for the 5-BTV vertical antenna we installed by the bunker. The results show that the 10 and 15 meter bands are tuned well. The 20 meter band is biased towards the low end, with 14.0 MHz at an SWR of 1.4 and 14.350 MHz at an SWR of 2.8. The 40 meter band is biased towards the high end, with 7.0 MHz at an SWR of 3.1, the minimum of SWR 1.5 at about 7.23 MHz, and 7.3 MHz at SWR 1.8. 80 meters is tuned to a best frequency of about 3.9 MHz (SWR = 1.8), with a probable usable range from 3.87 to 3.947 MHz (where the SWR reaches 3.0). Gary noticed one of the smaller radials for the vertical broke in the middle. Perhaps it had been set a little too tightly.

– After checking with the analyzer Gary did some operating through the afternoon and evening on 10 through 40 meters, mostly on FT8 digital mode and some SSB on 10 meters. He was able to tune on the digital portion of all of those bands with his FT-950. During that time he made about a hundred contacts, which give the club some exposure to the ham community. As of this writing, about 50 confirmations were received on LOTW and eQSL. The QRZ page counter increased by about a hundred during that time as well. Propagation was poor, so that most contacts were just around the US. We did get some DX to Germany, Italy, and New Zealand. Gary also checked into the 12:30 pm Weather Net on 146.970 MHz on the Pikes Peak repeater, which is at a distance of over a hundred miles.

– Dave Molter brought his trailer out and the crew loaded up most of the remaining surplus wood container parts for Dave to dispose of.

– Tony Bigbee came out for the first time on Sunday. Bill gave him a tour of the facility and Tony went right to work, cleaned out the pedestal base room, and sorted out a lot of the surplus hardware there. Thanks Tony, this was greatly needed.

– The Britain family from Haswell came out on Sunday afternoon. Bill, Paul, and Tony gave Mr. and Mrs. Britain and their two ~10 year old boys impromptu presentations and tours of parts of the facility. Mrs. Britain is a teacher and very interested in working with DSES on a school & student outreach program in the area.

– Dave again tried the VHF talk-in radio system (on 146.46 MHz) while coming in to the site. We had a clear contact with him from about mile marker 128 on Highway 96. Gary tried communicating through the talk-in system coming from the south from Las Animas. He contacted Ed and could be heard from the first transmission at the county line, which is on a ridge. Gary again tried talking to the system with Bill while going out, traveling north to Haswell and then west on Highway 96 past mile marker 128. Gary could hear Bill clearly along most of the route, but Bill had some difficulty hearing Gary. Bill suspects the problem may be at the audio of the phone receiver in the comm. trailer.

The team considered this a successful trip.

PHOTOS:

Gary using Dave’s antenna analyzer to record SWR (standing wave ratio) values on the 5-Band Trap Vertical antenna for the HF ham frequencies it covers.

Paul and Steve worked on covering the synchro trench from the communications trailer to the pedestal.
The synchro trench getting filled in.
Ed installed wiring in a conduit to power the outhouse. This will eventually be covered over.
Power conduit, looking back from the outhouse to the pedestal.
The outhouse. Ed installed conduits and additional wiring at the left, which will power the RV risers.
Dave loaded excess wood for disposal on his trailer Saturday evening. We watched a thunderstorm pass to the north.
A passing storm at sunset Saturday evening.
The rains seemed to clear the smoke and summer haze enough that we saw Pikes Peak in the distance.
Dave also cleared out the tumbleweeds from the bunker ramp.
The antenna for the VHF talk-in radio, located on the “dog house”.
The synchro indicator panel and the reinstalled the manual dish steering control panel in the rack, in the com trailer.
Rear view of the synchro indicator panel and manual dish steering control panel.
Bill’s test setup on the Analog Power supply for Dave’s System 1 controller.

View of the grain tower in Haswell over 5 miles away, seen from the site.
Steve’s antenna feed at the focus of the 60-foot dish antenna.

 

DSES Technical and Operations Meeting Minutes, 7-09-2018

DSES Technical and Operations Meeting Minutes, 7-09-2018

Minutes written by: Bill Miller, DSES VP and Acting Secretary

Location:  IHop/IHob, Constitution Street, Colorado Springs

Attendance:  Gary Agranat, Myron Babcock, Ed Corn, Glenn Davis, Floyd Glick, Dave Molter, Steve Plock, Bob Sayers, Bill Miller

Attending Remotely via TeamViewer:  Dayton Jones, Skip Macaulay, Jamie Riggs

Next Trips to site: 

  • July 21st site work trip.
  • Site work trip on an additional weekend before open house.
  • Open house trip for the group on Friday, August 10th thru Sunday August 12th with the public event on Saturday, August 11th.

 

Accuracy:  As always if I have misstated, omitted or misrepresented anyone please feel free to correct me.

Agenda:

  1. If Quorum present board vote on tower section disposition.
  2. Completion of outhouse project.
    1. Wiring
    2. Operation Briefing
    3. Toilet
  3. Closing of Synchro Cable Conduit trench
  4. Installation of RV electrical pedestals.
  5. Additional open house preparations.
  6. Tentative menu for Saturday in bunker.
  7. Questions and Comments

 

Meeting Minutes:

  • Steve and Ed only made $40 from the Ham Radio Mega Fest in Monument after Steve spent about $50 in diesel to haul the equipment back from the site. However, this did get most of the junk out of the bunker.  We still have a lot of site junk and surplus material to clean up.
  • Dave got a lot of the wood that was taken down last year cleaned up around the ramp.
  • We have an additional metal scrap pile in bunker needs to be cleaned out. Bill will help clean out and dispose of material.
  • Myron Treasures Report
    • Got $100 dues and donation from Skip at Centennial electronics
    • Got $50 dues from Don Lewis
    • $1383.22 in checking
    • $5731.02 in savings

Agenda Items;

  1. If we have a quorum at the meeting, present board to vote on tower section disposition. We have all board members present in this meeting except for Dr. Richard Russel.
    1. There are 9 – 10ft sections of ROHM 45 in Ray Uberecken’s yard that he would like to get removed.
    2. We have a Rohm 25 base above the bunker and we have 2 sections of on site and 2 more sections at Ray’s house, so we can still erect a 40-foot Rohm 25 tower at the bunker.
    3. Michael Lowe would like to have 5 sections of the ROHM 45 for the Pueblo Makers Space. A motion was made and seconded for the Board vote on giving the non-profit the excess ROHM tower sections that we don’t need.
    4. The board voted to give 5 sections of the ROHM 45 to Michael’s makers space project in Pueblo. Bill later let Michael know of this decision and Michael will arrange to pick up the tower sections from Ray’s property.

 

  1. Completion of outhouse project.
    1. Wiring: Ed has material to hookup power to the outhouse.
    2. Operation Briefing: Will have a rail road exhaust fan and a red light for occupancy indicator. Will brief the group on maintenance and operation of the facility.
    3. The second narrow door of the small building will have a pin on the inside to allow emergency exit should the main door become jammed or blocked.
    4. Toilet: Ed and Steve now have the chemical toilet and the service pipe installed.

 

  1. Closing of the synchro cable conduit trench: We need volunteers next trip of Saturday, 7/21 to cover the trench in before the open house. Most who will be at the work day said they would help.

 

  1. Installation of RV pedestals.
    1. Will setup best locations from last year’s open house RV parking.
    2. The RV hookups are for 20 Amp, 120V, and no ground fault. The connection will run from the outhouse electrical connection. They are not suitable for RV air conditioning loads.  The DSES will ask for a $10/night donation for RV plug in usage.
    3. Wiring: Will need to purchase additional materials for the RV electrical hookups. Ed, Steve and Myron will go to Colorado Electrical Supply this week to purchase the remaining material to install the RV Electrical pedestals.
    4. We will need to trench in the additional wires for the RV electrical permanently before winter.

 

  1. Additional open house preparations.
    1. Clean up garbage and scrap.
    2. Clean up under the comm. trailer.
    3. General cleanup and marking of hazards.

 

  1. Tentative menu for Saturday the 11th. Lunch and Dinner menu.
    1. Dave will bring the grill.
    2. Bill will bring the coffee mess with camp stove and another 10X10 canopy.
    3. Myron has been buying all the food in the past and he has had a donation pot but paying for the remainder out-of-pocket. The Board voted to cover food expense not covered by donations out of our bank account, so Myron is not stuck with the bill.
    4. Will have hotdogs on the grill for Saturday lunch for public.
    5. Steve will bring “Modified Brunswick Stew” for the dinner on Saturday night.

 

  1. Presentation for Saturday in bunker:
    1. Rich will provide the presentation agenda for the weekend.
    2. Gary will have a ham radio presentation and demo.
    3. Others may also present solar, and optical astronomy and other radio astronomy topics such as eddy bitty telescope.

 

  1. The pointing controls:
    1. System 1:
      1. Dave, Glenn and Bill are working to add analog power supply, motor control electronics and modified software program with tracking for system 1.
      2. Dave is reworking System 1 box at home and will reinstall on July 21st.
    2. System 2:
      1. Bill is working to complete software port and details for system 2 and will reinstall.
      2. Will add the Lenovo laptop for this.
    3. Dave and Bill will add 3 switch boxes to the DB 25 connections to the encoders and tracking output to make the systems selectable.
    4. Synchros: We have the azimuth synchro indicators working for azimuth position but still need to hook up the elevation synchros. Need a new access plate and Liquid-tight flexible conduit to route the wires from the Elevation encoder/synchro enclosure.

 

  1. Questions and Comments
    1. The GPS time base used in Skip Crilly’s SETI observations is a TN4 model from Spectrum Instruments. It has been sent back to Skip for repair or replacement before the next observation session in August.
    2. Need an announcement for the open house on August 11th in Eads, Sugar City, and Haswell businesses and in the Kiowa county newspaper. Need a one or two paragraph announcement for the open house.
    3. Ed had installed the telephone intercom and the talk in radio at the site on 146.46MHz simplex. Bill and Dave tested this on the last trip and had good audio and range as Bill drove out, almost out to Arlington on a hand held with rubber duck and good audio and copy. Great job on this to Ed!  We may increase the height of the antenna when the tower is erected for even more range.
    4. Gary placed the announcement for the Open House on our DSES website. And he placed an announcement in the August QST and on the ARRL website about the ham radio special event station to be operated during the Open House.

 

  • The meeting was adjourned, and Dave, Glenn and Bill spent an additional half hour after discussing the system 1. controller motor drive electronics design.

 

Submitted 7/16/2018:  Bill Miller, DSES VP and Acting Secretary

 

 

 

REASONS, a poem by Larry Maurice

I thought this might give a nice change of pace, and also be appropriate and fun. – Gary

REASONS
By Larry Maurice

Why do we do what we do?
Why is it done by so few?
The answer is vague, but maybe today
I’ll try and explain it to you

We do it for the FUN!
To watch the rising sun
To see the sparrow and the hawk on high at play
To watch the mountains rise from inside a darkened sky
To feel the muscle of the earth at the break of day

Great grey granite peaks
The place where your own spirit speaks
In a language that you interpret as you choose
We do it because we know that no matter how it goes
Life is not about the goods that you win or lose

We do it because we are never at our best
When we are setting down at rest,
Like those who only sit and plan and plan
But we are most at ease
When we are part of the breeze
Pitting ourselves and our stock against the land

In our life the job is never done
We always need another sun
It’s just handled for the moment
And we thrive on life’s hard rules
And we are often spoke as fools
But in the hardest job well done
There is contentment

Most of us take great pride
In the work
And the ride
And in the smugness of being where we want to be

I hope all of you
Need and love the work you do
And if not
Remember
It’s never too late
To set the Cowboy in you free.

Grassy Lake, Jackson Meadow, 1991

This poem appeared in a guide to learn CW (Morse Code) by Ron Stark KU7Y, distributed by QRP Amateur Radio Club International.

Plishner work site trip, June 16 & 17, 2018

Trip report by Bill Miller, with editing and photos by Gary Agranat. 

This is a report of our work at the Plishner radio telescope antenna site during the weekend of June 16 & 17, 2018.

Attendance: Gary Agranat, Paul Berge, Ed Corn, Michael Lowe, Bill Miller, Dave Molter, Steve Plock.

Vertical Multi-band Antenna Radials: Gary performed a set of SWR (Standing Wave Ratio) measurements with an antenna analyzer on the vertical multi-band antenna, which was installed last April for the ham radio station at the bunker. He then installed 17 radials at the antenna base.  On the next trip he plans to retake antenna analyzer measurements, and also do some digital radio operating, to compare characteristics before the radials were installed.

New Rest Room:  Steve Plock and Ed Corn continued work on the new rest room/out house.  This is a refit of one of the rail road buildings previously used for storage.  They added tie down cables to prevent it from succumbing to the winds.  It will be fit with a chemical toilet and there is a waste receptacle behind the building for easy dumping access.  This will greatly improve our facility for public visits such as the open house on August 11th.

Synchro Installation: Bill worked on the dish Az/El Synchro installation as a simple backup pointing system for the dish. On the previous trip Bill and Steve installed an additional 2” conduit from the Comm Trailer to the pedestal.  Myron had helped pull in the 15-conductor cable.  On this trip Ed Corn helped finish off the conduit and drilled 2” access holes in the trailer floor and pedestal.  Bill installed the cable up the pedestal structure and terminated it in the terminal box above the control deck.  He also terminated the other end on the synchro panel in the comm trailer.  The azimuth synchros were hooked up and they worked.  One problem remains with the fine azimuth synchro.  The Elevation synchro connection on the dish will be made in a future trip.

Pointing System 1: Bill and Dave examined what would be needed to complete system 1.  Bill has a linear power supply in the works to replace the noisy switcher.  He also has an amplifier and watch dog circuit for the control function in progress. Dave suggested removing the system 1 box on the next trip and bring it back to Colorado Springs to install these and other software modifications for Glenn to test.  Currently system 1 only has position feedback and no direct control.

Pointing System 2: System 2 currently has all the circuitry for full position reporting and tracking control. As reported last time, Bill is working to transfer programs between computers and working on the system 1 at home and will reinstall on the next trip.

Dish Restoration and Maintenance: Paul Berge came down Saturday afternoon and stayed for work Sunday. Paul checked our Synchro system and made some valuable suggestions. He worked on other maintenance items on the dish including making a rubber bellows and seal to keep the water and birds out of the multiple cables feeding down through the center of the azimuth axes.  He also started working on wiring and setting up the Elevation and Azimuth limit switches.

Other Items: Dave Molter finished the tear out of the 12-foot fiberglass dish and support concrete from Sue’s yard in Sugar City.  He transported it down to the site on his trailer and unloaded it for future use.   Bill and Dave pulled a vertical antenna and base insulator out of the pedestal and loaded it on Dave’s trailer.  Dave returned the antenna to Michael Lowe in Pueblo who originally brought it to the site.

 

The vertical 5-band antenna for the bunker ham radio station, with the radials installed.
Close-up of the radials for the vertical ham antenna.
The rest room after securing with guy wires.
Ed Corn preparing to install PVC drainage pipe at the new rest room.
The rest room with the drainage pipe installed.
The rest room with the drainage pipe installed. The effluent and chemical will drain to this excavated hole, which is now covered by railroad ties for safety. With Ed Corn and Steve Plock.
Inside the rest room, a repurposed railroad shed, after it was cleared out.
Looking up, inside from the base of the pedestal, to the third working level.
Bill Miller showing the terminal box at the third level of the pedestal.
Bill Miller with another junction at the third level of the pedestal.
Dave Molter bringing the pieces of the 12 foot satellite dish from Sugar City.
Bill Miller manually steering the 60-foot dish antenna, while Dave Molter monitors the position feedback.
Bill Miller manually steering the 60-foot dish antenna, while Dave Molter monitors the position feedback on the synchro panel.
Close-up of the synchro panel. It is designed to show the course & fine positions of the antenna elevation and azimuth.
Comm Trailer

While we worked on Saturday, there was harvesting in the surrounding fields.

 

The vertical ham antenna by the bunker, at the end of the work day Saturday.
Some rain passed through during the late afternoon Saturday.


 

Plishner Antenna Site Work Trip Report for May 18 – 20, 2018

We worked at the antenna site in Haswell from Friday May 18 through Sunday May 20, 2018.  We essentially worked in two teams.  The first team was at the site from Friday afternoon through Sunday morning, with some in that team just coming on Saturday. The second team worked Sunday afternoon.

Accomplishments for this work trip:

  • Beginning of work on a new toilet facility “outhouse” in the southwest corner of the site.
  • Aaron Reid brought his tractor. He excavated a large 5 1/2 foot hole, which will eventually be used to properly dispose the effluent from the outhouse. He also completed covering of the 600-foot trench that had been dug earlier to install the power line in the site. And he also excavated a new trench from the pedestal to the Comm. Trailer, to be used to lay control lines for our antenna pointing systems.
  • Initial checkout of the 5-band trap vertical antenna for ham radio at the bunker.
  • Removal of a 10-foot satellite dish antenna in Sugar City.
  • Continuing work on the dish antenna pointing control systems.

Contributors to this post are Steve Plock, Bill Miller, and Dave Molter, with additional writing and editing by Gary Agranat. Photos by Bill Miller, Gary Agranat, and Steve Plock.  Working on this trip also were Aaron Reid, Paul Berge, and Floyd Glick.

Thanks to everyone who helped on this trip.

Trip report by Steve Plock

I arrived Friday afternoon. Paul Berge arrived shortly after and Aaron Reid not long after that. We ate a little  dinner and turned in. Right around sundown it started raining. It rained most of the night and stopped around sunrise. Because it had rained all night it was pretty muddy outside. We helped Aaron unload his tractor off of his trailer.  We then started cleaning debris out of the 600′ trench ahead of the tractor that was pushing the low side hill made by the ditch witch down into the trench. We then placed the barrier tape into the trench ahead of the tractor which pushed the high side berm into the trench as well. We tromped through a lot of mud that morning.

Next we cleaned out the building that would become the new outhouse.

Then Steve and Paul ran an 85′ coax cable from the new vertical into the bunker. When Gary arrived he checked the antenna out using Ray’s Intellituner as a crude analyzer. It checked out OK on 80-40-20-15 and 10   meter phone portions of these bands.

Floyd Glick showed up and started helping out to get the outhouse up on the old platform that had the battery box building on it. We used a couple of  chains and the tractor and some boards to accomplish this. Next I marked the spot the Ed had wished the pit to be placed and Aaron dug it to a depth of about 5 ½’. All three of us worked together to cover the pit with railroad ties.

Next I marked the 2nd trench, from the pedestal to the Comm. trailer, after consulting with Paul to stay clear of the existing conduit. By that time everyone was pretty tired and turned in for another, night. Sunday morning everyone left before noon. I led Aaron north on County Road 20 until we hit CO Highway 96 up in Haswell. Told him to pick up Highway 287 north in Eads.

-Steve Plock

 

Site of our new toilet facility “outhouse”. We are repurposing a railroad shed. Aaron Reid excavated a 5 1/2 foot deep hole with his tractor behind the shed, where the effluent will properly be disposed. We plan to have the “outhouse’ in service by the time of our annual Open House in August. Our plans include installing electric light and heat.
The 5 1/2 foot deep hole excavated by Aaron Reid with his tractor. Old railroad ties were placed over the hole afterwards for safety.
We are cleaning out this former railroad shed for use as our new outhouse on the site. It had railroad electrical components and some debris accumulated over time. In the photo is Floyd Glick helping with the cleanup.
Steve Plock and Aaron Reid inspected the route for excavating a second trench, for the dish antenna pointing system Syncro wiring.
Ham Radio Vertical Antenna Check, by Gary Agranat

On our last trip we installed a donated 5-band trap vertical antenna for our ham radio station at the bunker. Although we had radial wires with the donation, we didn’t yet have time to install those.

Before I arrived on this trip, Steve Plock installed an 85 foot coax cable from the antenna base, through the doghouse, to the ham station in the bunker. Although he didn’t try to make any contacts, he reported good signal reception using the IC 706 on 40 and 20 meters, including DX from Europe. The IC 706 has an attached automatic antenna tuner, and he reported there was good tuning on all of the bands.

I decided to hold off installing the antenna radial wires, and instead check how well we could operate in the current set-up. I systematically checked the SWR and the ability to tune on all 5 wavelength bands of the vertical (80, 40, 20, 15, and 10 meters).  I confirmed we could tune well enough on all of the band spectrum except for the 20 meter Morse Code segment. I tried making some phone contacts but succeeded only with one. And for the IC 706 I didn’t have the right connector for my CW key.  I therefore instead set up a Yaesu FT-950 with a SignaLink digital interface matched for it.  With that I succeeded in making 30 FT-8 digital contacts, most on 40 and a few on 20 meters. I was able to do some DX (distance contacts) on 40 meters: IU8CNE (Italy) and LU5VV (Argentina). Plus we made one New Zealand contact, with ZL2IFB, on 15 meters, but otherwise DX conditions were poor. The other contacts were across the U.S. and to northeast Canada.  I also had one traditional Morse Code CW chat on 40 meters with K3WAS in Kansas.  And so the vertical antenna without the radials does work, and we do get out at least domestically.  The somewhat poor FT-8 DX suggests radials may be worth installing still, although I cannot rule out that we had poor band conditions.

-Gary Agranat

Gary Agranat WA2JQZ operating FT-8 at the K0PRT station in the bunker. Photo by Steve Plock from his smartphone.
The vertical antenna set up by the bunker, with coax feed from the doghouse.

Log of contacts:
K5BZI 20m SSB TX
K4SHA 40m FT8 AL
W6GRD 20m FT8 CA
K9ZJ 20m FT8 WI
VA3HP 40m FT8 ON, Canada
K2PS 40m FT8 FL
KG7RZD 40m FT8 WA
K3WAS 40m CW KS
K0CHW 20m FT8 SD
N9RS 40m FT8 WI
AB1HL 40m FT8 MA
K6SJT 40m FT8 CA
K7ZYV 40m FT8 MS
NA8N 40m FT8 OH
K6KHB 40m FT8 CA
WA6PHR 40m FT8 CA
AE8S 40m FT8 OH
N4RLG 40m FT8 KY
KB7ZDM 40m FT8 OR
KC1GWX 40m FT8 MA
WA2HIP 20m FT8 ME
VA3CTX 20m FT8 ON, Canada
ZL2IFB 15m FT8 New Zealand
VE2GYA 40m FT8 QC, Canada
N4ZI 40m FT8 TN
KB5DXO 40m FT8 MS
LU5VV 40m FT8 Argentina
N8NXG 40m FT8 FL
K4RGN 40m FT8 NC
WY7CDL 40m FT8 WY
IU8CNE 40m FT8 Italy
K9QVB 20m FT8 IL
AB5CA 40m FT8 TX

A benefit of using a digital mode like FT-8 is you can see feedback of where you are received, on the PSK Reporter website. This screenshot displays reports by other hams of where we were received for the previous 3 hours, at about 7:25 pm local time on Saturday (0125 GMT). The blues are for the 40 meter band, the yellow for 20, and the brown for 15 meters.
Trip Report by Dave Molter, for Sunday May 20, 2018

On Sunday I met Bill Miller in Sugar City, and tore down a 10 foot dish that was donated to DSES. The dish was left at the residence until a trailer can be provided to remove the parts. The base post was not removed from the concrete and will need to be done on a future trip. This effort also led to 3 more fiberglass 10 foot antennas identified which will be donated and obtained at a future date.

When we got to the site we energized the dish drives and observed noise on the elevation encoder lines shown by the LEDs flickering and watching the position signal on an Oscilloscope. Ferrite beads were installed around the elevation encoder lines. There was no change to the amount of noise present on the wires. The elevation readout cover was removed and the cable was removed from the encoder. The connector was opened to allow inspection of the wiring. The cable shield drain wire was temporarily jumpered to the frame ground. The signal noise was reduced.  The cable drain wire was connected to pin S of the encoder (Frame Ground). A jumper wire was also attached to the drain wire and connected to the encoder body. The mount was run in elevation and azimuth and the readout was stable, the LED did not flicker.   The dish control was transferred to the trailer.  The control panel was used to move the mount in azimuth and elevation. The readout computer was energized and the remainder of the day was spent looking for the paper that contained the logon to the portable computer.

It was observed that the electrical trench was backfilled. The trench between the tower and trailer was dug out. The ramp has a good sized amount of tumble weeds in residence.

– Dave Molter

Additional Details from Bill Miller, Sunday May 20, 2018

I arrived at Sugar City at 9 AM and met with Dave about 10:30.  We went to Sugar City contact’s (Sue) house and proceeded to disassemble the 10ft Fiber glass satellite antenna and mount in the back yard.  This took about 3 1/2 hours and we didn’t complete digging up the concrete foundation but got a good start on it.  This will be completed and the dish will be transported in a future trip.  Sue gave us contacts for a 10 ft mesh dish in Sugar City and for her daughter’s perforated dish in Rocky Ford.  Dave made contacts for 2 more fiberglass dishes in Sugar City.  Seems we can have all of these that we want for the asking and labor.

We didn’t get to the Plishner site until about 3:00 on Sunday and by then the previous crew of Aaron Reid, Steve Plock, Gary Agranat, Paul Berge and others had left the facility.

Dave and I set up to determine the cause and fix for the elevation encoder noise that we have been fighting for the last five months.  We took a methodical trouble shooting approach with scope and meter instrumentation.  We verified that the elevation encoder circuit was much more susceptible to the motor controller noise than the azimuth encoder circuit.  It was even susceptible to the Azimuth motor drive but to a lesser degree than to the elevation drive.  After trying several things we discovered by continuity checking that the Azimuth encoder wiring shield was grounded to the telescope structure at the encoder end but the elevation encoder wiring shield was open. We opened the elevation encoder box in the upper deck and attached the shield drain wire to the chassis ground with a clip lead.   This had a dramatic effect on the noise as seen by the scope and the 12 bit LEDs indicating the input signal state on system 1.  Seeing this, we permanently attached the shield drain wire to Pin “S” (Case GND) of the encoder connector and to the attachment screw on the encoder with a flying lead.  This substantially reduced the motor drive noise problem on the elevation encoder circuit and should provide much cleaner encoder signals to both system 1 and 2.  Of note: There is still a lot of HF noise on the system 1 electronics as indicated on the scope.  It appears to be from the small switch mode power supply in the box and the motor drives.  It may be wise to change out the small PS with one that is less noisy.  We were unable to check the Laptop program operation with System 1 due to a missing password.

We saw the trench that Aaron Reid had dug for the syncro cabling.  Thanks to Aaron for that.  I brought down a 350 foot spool of 15 conductor x 18awg wire for the syncro connection.  Unfortunately we had no suitable conduit to install in the trench so we will have to do that on a separate trip.  I left the spool of wire in the locked pedestal for when it can be installed.  The deal with OEM Electronics is to use what we need and return the rest for credit as soon as possible.  The approximately 160 ft of wire needed will be charged to Michael Lowe’s OEM credit that he established several years ago.

Two curious boys from Los Animus HS stopped by while we were working in the pedestal and we told them about the Dish, but not knowing them didn’t offer a tour.  Bill took their names and Email addresses for future contact.

Several spools of RG59u and a 4KW generator were left in the open after the clean out of the RR shed to be used for the outhouse. We moved the wire to the locked pedestal and Dave took the generator back to Springs to see if he could get it running.   We put food in the bunker away, locked up the site and left about 7:30PM.

-Bill Miller

12 Ft Fiberglass Dish in Sugar City
Dave Molter, 12 ft Dish Tear Down
Dave Molter, 12 ft Dish Tear Down
Dave and Sue at the 10ft Mesh Dish
Exposed Elevation Encoder and Syncro’s in the upper deck of the pedestal (Level 4).
Aaron’s Syncro Wiring Trench

Plishner Antenna Site Work Trip Report for April 22, 2018

The following is the report of our work trip to the Plishner antenna site in Haswell, Colorado on Sunday April 22, 2018.  This was written by Ed Corn KC0TBE, with additional contribution by Dave Molter AD0QD, and with editing and photos by Gary Agranat WA2JQZ.

* * *

Steve Plock (KL7IZW), Ed Corn, and Gary Agranat left the Ellicott Fire Station about 7:30 AM, and arrived around 9:30.  Dave arrived just a bit later. We met Paul Berge (K0DJV) at the site, who had traveled down on Saturday from Lyons and stayed overnight. Paul had done some clean-up in the bunker. And he cleaned out the pile-up of tumble weeds from the bunker ramp.

Steve worked on the locking system for the box with the azimuth/elevation hardware in the pedestal. He reports moving the dish antenna down to 0° elevation and back up to zenith with no read-out errors. The lock holds the door securely shut to form a good shield from motor EMI (interference).

Ed installed a stronger fence at the bunker ramp entrance.

Ed built a more robust gate for the bunker ramp. The strong winds at the site had unhooked the previous gate, which then allowed tumbleweeds to pile down the ramp again. Ed dragged two farm gates from west of the Communications Trailer to the bunker ramp. He set up the hinge pins for the gate, and Gary helped hang the gate.

 

We then covered the gates with field wire (in the gaps and along the bottom) to keep the tumble weeds from getting into the ramp area.

Ed then installed a VHF base antenna on the bunker dog house for the talk-in radio. The talk-in radio, K0PRT 146.460 MHz, is now up and working, with desk remote controls in the bunker and communications trailer.  Please note the desk remote control in the comm. trailer must be plugged into an outlet and powered on to operate. This arrangement keeps the RF at the bunker, and gives access to talk-in radio at the comm. trailer as well, without RF emissions near the 60-foot dish.

Ed installed a talk-in VHF radio system for the site. The remote control phones for the talk-in radio system are at the communications trailer (pictured) and in the bunker. The power plug-in for the comm. trailer phone is right next to it.

Gary continued work on the Hustler 5-BTV HF vertical antenna for the club station at the bunker. By the end of the day Gary had the vertical assembled and mounted on an anchor pole he installed with Dave’s help. The vertical is in place with non metallic guys for stability in the Plishner winds.

Gary doing final assembly of the vertical HF antenna.

Gary added these comments: “I assembled the antenna with lengths used by the previous owner, but noted the originally specified lengths from the manual. Some worn parts were replaced with parts provided by Dave, and some machine screws were replaced with stainless steel ones. We salvaged a conduit pipe for a base mount, and Dave drove it into the ground (a few feet deep) northwest of the dog house, at a distance of more than 20 feet from nearest obstacles. Dave and I then mounted the antenna on the base…”

The Hustler 5 Band Vertical Trap Antenna mounted to the base post near the bunker.

“… One of the two leads of the pigtail connection to the antenna at the base came loose. With Steve’s help we removed the pigtail, and I soldered a new lug connector, and reconnected the pigtail.  I then used Dave’s antenna analyzer to map the SWR – frequency response of the antenna.  That was just an initial check, as we have not yet installed the radials. With the current lengths, the antenna is resonant in the 80 and 40 meter bands, but not the 20, 15, and 10 meter bands. At the end of the day, the whole team present helped install non-conducting guy ropes. Those will provide the lateral structural support against the expected winds.”

The team set up the HF vertical ham antenna with non-conductive guy ropes northwest of the bunker. The antenna will add 10, 15, 20, and 40 meter band capability to the bunker ham radio station. The bunker already has 80 and 160 meter dipole antennas. L to R: Dave, Ed, Steve, and Paul.

Dave unloaded a truck full of concrete blocks,  bagged cement, and mortar mix for use in the retainer wall extension at the bunker.  Then Dave and Paul used the rest of the day to work on the antenna dish controls. They also lowered the 2 old drive motors from the pedestal control deck to the floor in preparation for removal from the site to salvage.

Dave walking back to the pedestal of the dish antenna.

Dave added these comments: “I delivered 22 concrete blocks, 2 bags of type S mortar mix, and 6 bags of concrete mix. That makes a total of about 65 blocks to use when we resume the wall building. Paul Berge was at the site, and we discussed the installation of the VFD for the elevation axis drive. His insight answered many questions I had and had never gotten answers to. We stepped through the wiring of the VFD and cabinet wiring, and how the remote unit in the trailer and hand paddle were wired to the cabinet. We soldered permanent ground wires with terminal lugs onto the shields of the Az and El brake cables, and onto the shield to the elevation motor drive. All shields were terminated to the main cabinet ground connection. There appeared to be no change in the observed noise present on the LEDs while no signal was present.”

“Paul and I lowered the two motors that were on the 03 (top) level of the pedestal to the ground level. There is one more motor on the 02 level that Paul believes is a spare for the installed motor.”

“A mounting post was driven in the ground about 35 feet west of the main support for the for 80 meter dipole. Gary had assembled the 5 BTV vertical antenna, and the group mounted the antenna to the post, and installed 3 guy lines.”

 * *

Ed and Steve talking in the Com Trailer, at the end of the day. Steve created a chart map of astronomical radio sources, which he placed in the Com Trailer (the white chart behind the remote call-in phone).
The commercial power feed at the site entrance on County Road 20, installed earlier this year.
The completed, more robust, fence at the bunker.

Paul stayed over Sunday and Monday nights, traveling home on Tuesday. He spent Monday doing routine maintenance and clean-up on the dish drive systems, which had been delayed and was past due.

Thanks to everyone for a very productive work weekend at the site.

Ed KC0TBE

 

 

 

DSES All Members Meeting April 14, 2018

This is the slide presentation for our All Members Annual Meeting on April 14, 2018. This was presented by Dr. Richard Russel, our out-going president.

DSES All Members Meeting 2018

The content includes:

  • The results of the Executive Board election
  • The Treasurer’s Report
  • Club accomplishments of the past year (of which there are many)
  • List of current projects
  • Science and published paper highlights
  • Outreach and communications
  • New Officer nominations / elections / appointments *

The Annual Meeting was held at the La Casa Fiesta Restaurant in Monument, CO.

The next official meeting is an open Executive Board Meeting on Friday evening, May 4, 2018 at 5:30 pm. The location is the IHOP just east of Powers Blvd. on Constitution Ave. in Colorado Springs. The General Membership is welcome to attend. Unfinished business and plans for the upcoming year will be discussed.  (*) Also the elections will be recertified at the meeting.

 

 

Annual 2018 Members Meeting Invitation

Dear DSES Members,

Please attend our annual all members meeting to be held on Saturday, April 14th at 1:00PM in Monument Colorado at the La Casa Fiesta Restaurant www.lacasafiesta.net in the Garden room. This should make it a little more convenient for our northern Colorado members to attend.

We have completed our annual partial board election with the election or retention of the following four board members:

Gary Agranat, Myron Babcock, Steve Plock, and Dr. Richard Russel.

Seven Board Members are elected for a two-year term with 4 and 3 elected on alternate years. The other three board members elected on the last election cycle are, Floyd Glick, Dave Molter and Bill Miller.

At the annual meeting we will elect the officer seats for President, Vice President, Treasurer, and Secretary from the board members, and we will also give the annual activities report and treasurers report as well as discuss future project plan and new business.

We hope to see you there.

Regards,

Bill Miller
DSES Secretary

Directions:
From I25 Take exit 161 for CO-105 toward Monument/Palmer Lake, 0.5 mi
Turn left onto 2nd St, 0.6 mi
Turn right onto Front St
Destination will be on the right, 177 ft
La Casa Fiesta New Mexican Restaurant
230 Front St, Monument, CO 80132

Fiber Cable Installation

These are photos, shared by Steve Plock, from the installation of the 100 meter fiber optic cable during the first week of March. The new cable runs from the antenna feed to the com trailer, and replaces a coax cable. A 50-foot lift was rented, to run the cable to the antenna feed. Ed Corn worked from the lift bucket.

The installation was originally scheduled for Monday March 5th, but the winds were too strong. The winds were not as strong the next day, though still a challenge, and they did the installation then.

The fiber optic cable enables a higher data rate, and also eliminates a significant source of noise.

Skip Crilly, Monday March 5, 2018.
Ed Corn working from the bucket. Tuesday March 6, 2018.
Ed working from the bucket, with Floyd Glick and Bill Miller watching on the ground. Tuesday March 6, 2018. Also present were Glenn Davis and Paul Berge.